Note.—This resolution is in the Bulletin. Please notify formal errors so that corrections BOARD MEETING OF: CALENDAR NO.: PREMISES: ACTION OF BOARD THE VOTE — Affirmative: Vice-Chair Commissioner Negative: Recused: Chair Perlmutter THE RESOLUTION — This is an application construction pursuant pursuant to Z.R. § 72-21, industrial building to A public hearing 2020, after due notice decision on December The Premises are Commerce Street and in Brooklyn. With approximately Street, a depth ranging square feet of lot area, residential building. The Board has December 23, 2003, Board granted a variance, an existing six-story that all work substantially objections, filed with implemented prior to potential hazardous residents: (1) Ground-penetrating gallon petroleum underground site; (2) Testing the fluid (3) Phase II investigation suspect liquid observed above-ground storage Premises be maintained in the Premises be according to BSA-approved applicable fire safety residential spaces comply Code, with compliance Buildings; the conditions substantial construction the approval be limited to specifically cited and the approved plans related to the specific ensure compliance with Resolution, the Administrative under its jurisdiction related to the relief granted. Judicial proceedings, the Board’s decision applicant submits that, of the final order in Hook/Gowanus Chamber Standards & Appeals, On May 1, 2012, granted an extension expiring May 1, 2016, completed by May 1, By letters dated 2015, under the subject modifications to the Board-approved On December 5, Board granted an extension years, expiring May 1, By letter dated number, the Board approved plans. The time to complete now seeks an extension The applicant represents the applicant discovered who failed to perform of the mechanical design five months engaging to complete the approximately one year currently 95 percent Based upon its that the requested appropriate with certain Therefore, it is Resolved, does hereby amend amended through December of the resolution shall construction for three the current state of emergency York resulting from November 1, 2023, on the Premises THAT any graffiti THAT 48 hours; parking shall THAT the applicant THAT measures; all exits from THAT comply with applicable compliance to be determined the above THAT occupancy; a certificate THAT calendar number (“BSA three years and an additional of emergency declared from an outbreak of novel all conditions THAT by the Board remain this approval THAT response to objections the approved THAT the portions related to the Department THAT all other applicable Administrative Code irrespective of plans or Adopted by the Board This the Board
256-02-BZV
Extension of Time to Complete Construction of a previously granted Variance (§72-21) for the conversion of a vacant six story manufacturing building for residential (UG2) use, which expired on May 1,
BSA Decision
Full decision PDF
View PDF →ZR Sections Cited (2)
Decision Excerpt
Want to dig deeper into 256-02-BZV?
Ask Zonable about the reasoning, similar precedent cases, or how it applies elsewhere.