Note.—This resolution is in the Bulletin. Please notify formal errors so that corrections BOARD MEETING OF: CALENDAR NOS.: PREMISES: ACTION OF BOARD THE VOTE — Affirmative: Chair Commissioner Commissioner Negative: THE RESOLUTION — This is an application and Procedures (“the complete construction, variance granted pursuant of two three-story, single-family A public hearing 2021, after due notice decision on February inspections of the Premises The Premises are between Atlantic Avenue district, in Brooklyn. Underhill Avenue, 80 the Premises are currently The Board has January 12, 2016, when, granted a variance, under district, the construction contrary to Z.R. § substantially conform with the application; accordance with Z.R. granted by the Board DOB/other jurisdiction approved only for the DOB not issue a certificate provided DOB with certified Remedial Closure all other applicable Administrative Code, jurisdiction irrespective relief granted. The time to complete now seeks an extension. two years after the expiration applicant requests a of § 1-07.3(c)(2), of application. Since the Board’s not commenced construction, initial variance, the speculative residential because of its location proximity to the traffic represents that the market back to the development area. The applicant further for single-family homes the pandemic-induced with outdoor green space in the market for newly to loud, busy intersections At hearing, the the applicant’s construction submitted an updated and anticipated completion Based upon its that the requested extension variance is appropriate Therefore, it is Resolved, does hereby waive its resolution dated January the resolution shall read: for four years, to expire substantial THAT with Z.R. § 72-23; DOB shall THAT applicant has provided Engineer-certified Remedial substantial THAT by an inspection by the February 28, 2026; the above THAT occupancy; a certificate THAT calendar number (‘BSA obtained within four this approval THAT response to objections the approved THAT the portions related to the Department THAT all other applicable Administrative Code, jurisdiction irrespective relief granted.” Adopted by the Board
221-14-BZII
Extension of Time to Complete Construction of a previously approved Variance (§72-21) to permit the construction of two 3-story single family residences which expired on January 12, 2020; Waiver of th
BSA Decision
Full decision PDF
View PDF →ZR Sections Cited (3)
Decision Excerpt
Want to dig deeper into 221-14-BZII?
Ask Zonable about the reasoning, similar precedent cases, or how it applies elsewhere.