2022-3-BZY
Extension of time (§11-332) to complete construction of a minor development commenced under the prior zoning. M1-2D zoning district
July 10, 2023
Hearing date
Address
4923 Second Avenue
Community Board
Brooklyn Community Board 7Extension of time (§11-332) to complete construction of a minor development commenced under the prior zoning
Extension of time (§11-332) to complete construction of a minor development commenced under the prior zoning. M1-4/R6B zoning district
Application to acquire vested rights under common law requesting the renewal of all building permits relating to the proposed development of a transient hotel. M1-3 zoning district.
Extension of time (§11-332) to complete construction of a minor development commenced under the prior zoning.
Extension of time (§11-332) to complete construction of a minor development commenced under the prior zoning. M1-5 zoning district
Extension of time (§11-332) to complete construction of a minor development commenced under the prior zoning.
Common Law Vesting application requesting that the Board determine that the property owner secured a vested right to complete construction of a development prior to the adaption of a zoning text amend
Extension of Time to Complete Construction and Obtain a Certificate of Occupancy of a previously approved Common Law Vesting application which expires on December 17, 2023. M1-2 zoning district.